Status: | Operational (2021) |
Location: | In the Frisian part of the IJsselmeer, near Breezanddijk |
Owner: | Windpark Fryslân Holding B.V. (Windpark Fryslân Beheer B.V. (85%) and the province of Fryslân (15%) via Fryslân Hurdewyn B.V |
Production capacity: | 383 MW |
Annual yield: | 1.5 TWh |
Turbines: | 89 x Siemens Gamesa |
Turbine power: | 4.3 MW |
Hub height: | 115 m |
Tip height: | 180 m |
Rotor diameter: | 130 m |
Blades: | 63 m, made in Morocco |
Foundation piles: | Monopiles: 40 m /4.5 m diameter, by EEW SPC. No Transition Piece |
External platform: | AARSLEFF BIZ Sp. Z.o.o. Świnoujście, Poland, Platform cranes by Wesco IJmuiden |
Internal platforms: | Amicon (previous Bijlsma Constructie BV) in Winsum, NL |
Tower sections: | 3 per turbine, o.a. Welcon, Give, Denmark |
Inter-array cables: | 33 kV, 90 km, by TKF in Lochem |
Export cables: | 55 km of 110 kV cables by Prysmian in Delft |
Grid operator: | TenneT |
Substation onshore: | At Breezanddijk, 2 transformers by Siemens Energy in Austria |
Main vessels used: | Sarens Soccer Pitch, WimTom (installation), Wijnne Barends’ Lady Alida, Lady Amalia, Lady Anne Beau (monopile transport)…. |
Ports: | Alaskahaven in Amsterdam (TMA Logistics), Flevokusthaven in Lelystad, Oude Zeug in Wieringerwerf, Industriehaven Harlingen, Werkhaven Urk. Maintenance port is Flevohaven. |
Project management: | Ventolines |
Main contractors: | Zuiderzeewind (Van Oord Offshore Wind & SGRE) |
Power purchasers: | Eneco |