Status: | Commissioned in 2021 |
Location: | 55 km off the coast of Vlissingen |
Owner: | Blauwwind (Partners Group (25%), Swiss Life Assets Manager (20%), Shell (20%), Eneco (10%), DGE (15%) and Luxcara (10%) |
Production Capacity: | 731.5 MW |
Annual yield: | 3 TWh |
Turbines: | 77 x MHI Vestas V164-9.5 MW |
Turbine power: | 9.5 MW |
Hub height: | m |
Tip height: | m |
Rotor diameter: | 164 m |
Foundation piles: | Monopiles by Sif Group |
Transition pieces: | N/A |
Inter-array cables: | Prysmian, 66 kV |
Export cables: | 117 km, 220 kV |
Main vessels used: | Aeolus (turbines, foundations), Acta Centaurus, Seaway Strashnov (OHVS), Nexus (cables) |
Grid operator: | TenneT |
Substation offshore: | 700 MW Borssele Beta, by HSM Offshore |
Substation onshore: | In Borssele |
Maintenance port: | Vlissingen |
Main contractors: | Van Oord (BoP) |
Power purchasers: | Electricity is sold by Shell Energy Europe Ltd (50 %) & Eneco (50 %). Confirmed purchasers: Microsoft Corporation (90 MW) |
Project website | Click here |