Moonfish returns for Hollandse Kust (west Alpha) subsea cable burial

At the end of last week, Belgian contractor Jan de Nul’s intertidal trenching vehicle Moonfish returned to Heemskerk beach to bury TenneT’s subsea cables for the Hollandse Kust (west Alpha) connection.

Meanwhile, all four sea cables have been pulled in under the dunes by Jan de Nul. The first two cables for Hollandse Kust (noord) are already up to the socket at a safe depth in the seabed. Once the Moonfish returns to work, it will first bury cable number four, intended for the Hollandse Kust wind farm (west Alpha), to be built 50 kilometres off the coast of Egmond aan Zee, in the beach and seabed. This will be followed by the remainder of cable number three, which has already been partially buried.

Preparations

In anticipation of the digging work, the necessary preparations have already been made offshore. On the route for the fourth sea cable, there is a large and rigid sand package off the coast that makes the Moonfish excavation work difficult. Jan de Nul solved this by driving in sheet piling plates, which loosened the sand a little. The sheets were removed again immediately after being driven in. Preparatory excavation work is also being carried out on the beach this weekend.

Window of opportunity

When the weather and the tide is good (no waves bigger than 1 meter), the cable will be loaded into the Moonfish and the vehicle will be coupled to the floating water pipe. The floating water pipe will pump water to the powerful water jets on the Moonfish’s long sword. With these, it makes an eight-metre-deep trench in the seabed into which it immediately lays the cable. The trench is then immediately closed.

Once the cable is at depth in the Heemskerk beach, the receiving pit is removed and refilled with sand. The Moonfish then buries the cable to a distance of three kilometres off the coast. There, the subsea vehicle UTV1200 takes over the job until it reaches the ‘socket at sea’. This TenneT substation is located 50 kilometres off the coast of Egmond aan Zee. On this part of the route, the cable is less deep; at about 2.5 – 3 metres.

Last piece

For the third cable, the Moonfish is again sailed to the coast on a ship. It then travels the last kilometre to the beach independently over the seabed again. Then the loading and coupling process repeats itself, allowing the robotic vehicle to bury another part of sea cable three until the UTV1200 takes over the job there too. Source: TenneT Image: ©Jorrit ‘t Hoen