OranjeWind (Hollandse Kust West VII)

Status:Under development. Offshore construction is scheduled to start in 2026, with full commissioning expected in early 2028. 
Location:Approximately 53 kilometres off the coast from IJmuiden, province of Noord-Holland
Owner:RWE & TotalEnergies (50-50)
Production Capacity: 795 MW
Annual yield: Around 3 TWh
Turbines: 53 x Vestas V236-15.0 MW
Turbine power:15 MW
Hub height:
Tip height:
Rotor diameter:
Foundation:TP-less Monopiles – by Sif Group
Towers:
Inter-array cables: Twentsche Kabelfabriek (TKF)
Export cables: Orient Cable
Main vessels used:
Installation vessels Les Alizés & Voltaire
Grid operator: TenneT – Hollandse Kust (west Beta) connection
Substation offshore: 700 MW, built by Smulders.
Substation onshore: In Wijk aan Zee
Maintenance port:
Main contractors: Jan De Nul -transport and installation of foundations and wind turbines, NBOS (Boskalis Offshore Energy & Orient Cable ) – export cable laying, Heerema – installation offshore substation
Power purchasers:
Additional features:OranjeWind is the first offshore wind farm in the Netherlands with system integration. In order to achieve system integration, OranjeWind will develop, realise and test new developments and innovations. These innovations include offshore floating solar by SolarDuck, a subsea lithium-ion battery, LiDAR power forecasting system and a subsea hydro storage power plant off-site.