Jumbo Offshore has completed its Transition Piece (TP) transport & installation (T&I) scope on the Yunlin Offshore Wind Farm in Taiwan.
Jumbo had been contracted by wpd offshore subsidiary Yunneng Wind Power Co., Ltd. to transport and install 80 TPs. Jumbo completed its scope ahead of schedule.
For its role on the project, Jumbo Offshore deployed its DP2 Heavy Lift Crane Vessel Jumbo Javelin. Prior to undertaking the project, Jumbo Offshore carried out extensive project preparations to ensure a smooth, reliable project execution.
Following this, Jumbo Javelin was outfitted in a project-specific set-up. This included the Jumbo Fly-Jib modular crane boom extension. This feature can be mounted on a Jumbo J-Class vessel to increase the lifting height. With this, the vessel was provided with the capability to lift the 27 m high TPs.
Jumbo Javelin performed the final TP installation on Friday, August 23. The vessel was loaded out with TPs in Kaohsiung, transporting up to four 450t TPs at one time.
Versatile execution
Water depths at the Yunlin OWF vary between 7 and 35m. The shallower water location are not suitable for installation in DP mode. Therefore, Jumbo Offshore switched between installation on DP and installation on anchors, making full use of the vessel’s versatility.
Yunlin OWF
The Yunlin OWF is located in the Taiwan Strait, between 8 and 17 km from the coast of Taiwan. Covering an area 82km2, the OWF comprises 80 WTF (wind turbine generators), able to provide up to 640 MW clean electricity, sufficient to power 600,000 Taiwanese households. Source: Jumbo