Hollandse Kust (west) Alpha receives grid readiness certificate ahead of schedule
The grid connection for Hollandse Kust (west) Alpha is officially ready for commissioning. Whereas completion was scheduled for the first quarter of 2024, TenneT received the grid readiness certificate from DNV before the holidays in 2023. This means that wind...